Rehabilitation of Distribution Networks – Perip Lot 4

Power Efficiency and Reliability Improvement Project (PERIP) – Lot 4: Rehabilitation of Distribution Networks at Maputo and Matola (Medium and Low Voltage Systems). Work financed by World Bank.

Main Quantities

  • 1250 wooden posts for Medium Voltage lines;
  • 1300 concrete posts for Medium Voltage lines;
  • 550 km of conductor for the execution of approximately 190 km of Medium Voltage lines;
  • 105 km of ADSS (optical fiber);
  • 100 MT/LV transformers;
  • 5000 wooden posts for Low Voltage lines;
  • Connection of 6,000 new consumers.
  • Two 25 m high metal lattice towers for crossing the river.
See all Details

Client: EDM – Electricidade de Moçambique
Contract type: Unit Price
Construction Date: 2020 – job in progress
Cost: USD 11.177.344,86

Request more Information

Fill out the form to the side for additional information.

Seth will contact you as soon as possible.

Seth, SA requests your consent to register and process the personal data provided by our services in the processes of sending the requested information. We guarantee that the treatment and use of the information collected will be exclusively for this purpose, the consent being freely revocable and at any time you can exercise your rights of access, rectification, opposition and elimination through the email comunicacao@seth.pt. If you agree, please click on “Consent to data collection and processing”.

Pesquisar

Search